Free PMP practice test: 20 questions with worked answers

Try a sample question

A project has earned value (EV) of $40,000 and an actual cost (AC) of $50,000. What is the cost performance index (CPI)?

Free · 20 questions · answers explained · no sign-up

This free PMP practice test has 20 original questions in the style of the PMI exam: earned value and critical path calculations, agile and predictive scenarios, stakeholders, risk, contracts and the business environment. Every answer is explained, with the mistake most people make. These are not PMI questions. PMI updated the exam in July 2026, so also check its current exam content outline.

20
original questions, worked
3
domains: people, process, business environment
July 2026
exam update
Free
no sign-up

Last checked · Exam update and weights as reported from PMI pages in search results; confirm on pmi.org. Checked 23 November 2026

By the LifeScore Editorial Team · Updated · How we check facts · How this is scored

What do PMP practice questions look like?

Short scenarios in which you are the project manager and must pick the best next action, plus a few calculations. Several options can look reasonable, so the skill is choosing the best one.

  1. CCAT-style question 1 · Process: cost performance

    A project has earned value (EV) of $40,000 and an actual cost (AC) of $50,000. What is the cost performance index (CPI)?

    1. A0.8
    2. B1.25
    3. C0.2
    4. D10,000
    Worked answer

    A: 0.8. CPI = EV ÷ AC = 40,000 ÷ 50,000 = 0.8. Below 1 means the project is over budget.

    The trap: Inverting the formula (1.25), which would suggest the project is under budget.

  2. CCAT-style question 2 · Process: schedule performance

    EV is $40,000 and planned value (PV) is $50,000. What is the schedule performance index (SPI)?

    1. A0.8
    2. B1.25
    3. C−10,000
    4. D0.2
    Show the answer

    A: 0.8. SPI = EV ÷ PV = 0.8. Below 1 means the project is behind schedule.

    The trap: Using AC where PV belongs.

  3. CCAT-style question 3 · Process: estimate at completion

    The budget at completion (BAC) is $100,000 and the CPI is 0.8. Assuming the current cost performance continues, what is the estimate at completion (EAC)?

    1. A$80,000
    2. B$100,000
    3. C$125,000
    4. D$180,000
    Show the answer

    C: $125,000. EAC = BAC ÷ CPI = 100,000 ÷ 0.8 = $125,000.

    The trap: Multiplying BAC by CPI (80,000), which would predict a cost under budget for a project that is over it.

  4. CCAT-style question 4 · Process: critical path

    Task A (3 days) is followed by B (4 days) and C (6 days) in parallel. D (2 days) follows both B and C. What is the critical path duration, and the float on B?

    1. A11 days; 2 days of float
    2. B9 days; 0 days of float
    3. C11 days; 0 days of float
    4. D15 days; 2 days of float
    Worked answer

    A: 11 days; 2 days of float. A-C-D takes 3 + 6 + 2 = 11 days, and A-B-D takes 9. The critical path is 11 days, and B can slip 2 days without delaying the project.

    The trap: Adding every task (15 days). Parallel tasks do not add.

  5. CCAT-style question 5 · Process: three-point estimate

    Optimistic 4 days, most likely 6 days, pessimistic 14 days. What is the PERT estimate?

    1. A6 days
    2. B7 days
    3. C8 days
    4. D9 days
    Show the answer

    B: 7 days. (O + 4M + P) ÷ 6 = (4 + 24 + 14) ÷ 6 = 42 ÷ 6 = 7 days.

    The trap: Taking a simple average (8 days). PERT weights the most likely value four times.

  6. CCAT-style question 6 · People: communication channels

    A project team has 6 people. How many communication channels exist?

    1. A6
    2. B12
    3. C15
    4. D30
    Show the answer

    C: 15. n(n − 1) ÷ 2 = 6 × 5 ÷ 2 = 15.

    The trap: Forgetting to divide by 2 (30).

  7. CCAT-style question 7 · Process: risk value

    A risk has a 20% chance of happening and would cost $50,000 if it did. What is its expected monetary value?

    1. A$10,000
    2. B$20,000
    3. C$40,000
    4. D$50,000
    Show the answer

    A: $10,000. EMV = probability × impact = 0.20 × 50,000 = $10,000.

    The trap: Quoting the full impact as if the risk were certain.

  8. CCAT-style question 8 · People: stakeholders

    A senior executive has high power over the project but low interest in the details. What is the usual engagement approach?

    1. AKeep satisfied
    2. BManage closely
    3. CKeep informed
    4. DMonitor only
    Show the answer

    A: Keep satisfied. High power with low interest means keep satisfied: do not overload them, but avoid surprises.

    The trap: Choosing "manage closely", which is for high power and high interest.

  9. CCAT-style question 9 · Process: agile roles

    In Scrum, who is responsible for ordering the product backlog?

    1. AThe product owner
    2. BThe Scrum Master
    3. CThe developers
    4. DThe project sponsor
    Show the answer

    A: The product owner. The product owner is accountable for the product backlog and for ordering it to maximise value.

    The trap: Picking the Scrum Master, who coaches the team and removes impediments, not who decides priorities.

  10. CCAT-style question 10 · Process: agile events

    What is the main purpose of the sprint review?

    1. ATo inspect the increment and adapt the product backlog
    2. BTo plan the next sprint's tasks
    3. CTo assess individual performance
    4. DTo improve the team's way of working
    Show the answer

    A: To inspect the increment and adapt the product backlog. The sprint review looks at what was built with stakeholders and updates the backlog. Improving how the team works is the retrospective.

    The trap: Confusing the review with the retrospective.

  11. CCAT-style question 11 · People: leadership

    A servant leader is most likely to:

    1. ARemove impediments so the team can work
    2. BAssign every task personally
    3. CApprove every decision
    4. DEnsure the team follows a fixed script
    Show the answer

    A: Remove impediments so the team can work. Servant leadership focuses on enabling the team: clearing obstacles, coaching and supporting.

    The trap: Mistaking leadership for control.

  12. CCAT-style question 12 · People: conflict

    Two senior team members disagree about a technical approach. Which technique usually gives the most lasting resolution?

    1. ACollaborate (problem solve)
    2. BForce
    3. CSmooth
    4. DWithdraw
    Show the answer

    A: Collaborate (problem solve). Collaborating brings both views together to find a solution that addresses the real issue, and it builds commitment.

    The trap: Forcing a decision, which resolves it quickly but leaves resentment.

  13. CCAT-style question 13 · Process: change control

    A stakeholder asks for a change in scope in a predictive project. What should the project manager do first?

    1. AEvaluate the impact and follow the integrated change control process
    2. BRefuse the request
    3. CMake the change immediately
    4. DAsk the team to work overtime
    Worked answer

    A: Evaluate the impact and follow the integrated change control process. Assess impact on scope, schedule, cost, risk and quality, then submit through change control for a decision.

    The trap: Saying yes to keep the stakeholder happy before knowing the impact.

  14. CCAT-style question 14 · People: team development

    In Tuckman's model, which stage follows storming?

    1. ANorming
    2. BForming
    3. CPerforming
    4. DAdjourning
    Show the answer

    A: Norming. The stages run: forming, storming, norming, performing, adjourning.

    The trap: Skipping norming and jumping to performing.

  15. CCAT-style question 15 · Process: scope

    A developer adds a feature nobody asked for because they think the customer will like it. This is called:

    1. AGold plating
    2. BScope creep
    3. CValue engineering
    4. DFast tracking
    Show the answer

    A: Gold plating. Gold plating is the team adding extras beyond the agreed scope. Scope creep is uncontrolled growth in scope, usually through requests.

    The trap: Calling every unplanned addition scope creep.

  16. CCAT-style question 16 · Process: contracts

    Under a firm-fixed-price contract, who carries the cost risk?

    1. AThe seller
    2. BThe buyer
    3. CBoth equally
    4. DThe project manager
    Show the answer

    A: The seller. The price is fixed, so if costs overrun the seller absorbs it. In cost-reimbursable contracts the buyer bears more of the risk.

    The trap: Assuming the buyer pays any overrun.

  17. CCAT-style question 17 · Business environment: compliance

    Midway through the project, a new regulation affects the product. What should the project manager do first?

    1. AAssess the impact on scope, schedule and cost, and inform the sponsor
    2. BIgnore it until the project ends
    3. CCancel the project
    4. DWait for the team to raise a change request
    Show the answer

    A: Assess the impact on scope, schedule and cost, and inform the sponsor. External changes such as regulations need to be analysed for impact and raised with the sponsor and stakeholders, then handled through change control.

    The trap: Waiting for someone else to raise it.

  18. CCAT-style question 18 · Business environment: benefits

    A project delivers on time and on budget but the business case benefits are not realised. What does this show?

    1. ADelivery success is not the same as value
    2. BThe project failed on cost
    3. CThe schedule was wrong
    4. DThe sponsor was inactive
    Show the answer

    A: Delivery success is not the same as value. On-time, on-budget delivery means the outputs were produced. Value comes from benefits, which the project manager should track against the business case.

    The trap: Assuming that meeting the triple constraint means success.

  19. CCAT-style question 19 · Process: tailoring

    A project builds hardware and software. Hardware needs fixed specifications, while software requirements keep changing. What is the best approach?

    1. AA hybrid approach, tailored to each part
    2. BPredictive for everything
    3. CAgile for everything
    4. DDelay the project until requirements are fixed
    Show the answer

    A: A hybrid approach, tailored to each part. Tailor the approach: plan the hardware predictively and develop the software iteratively, and manage the interfaces between them.

    The trap: Applying one approach to the entire project because it is the standard.

  20. CCAT-style question 20 · Process: risk response

    A company buys insurance against a risk of fire damage. Which response strategy is this?

    1. ATransfer
    2. BAvoid
    3. CMitigate
    4. DAccept
    Show the answer

    A: Transfer. Transfer shifts the impact of a risk to a third party, usually through insurance or a contract.

    The trap: Calling it mitigation. Insurance does not reduce the chance of fire.

These questions were written for this page. They are not PMI questions. They show the kinds of reasoning the exam rewards; they do not predict a score.

Which PMP formulas should I memorise?

Know the earned value set, the three-point estimate and the communication channels formula. They are quick to learn and appear as short calculations.

Common PMP formulas
MeasureFormulaReads as
Cost variance (CV)EV − ACNegative means over budget
Schedule variance (SV)EV − PVNegative means behind schedule
CPIEV ÷ ACBelow 1 means over budget
SPIEV ÷ PVBelow 1 means behind schedule
EAC (typical)BAC ÷ CPIForecast if current cost performance continues
PERT estimate(O + 4M + P) ÷ 6Weighted average
Communication channelsn(n − 1) ÷ 2Grows quickly with team size

How do I choose between two reasonable PMP answers?

Pick the answer that analyses first, involves the right people and follows the process, rather than the one that jumps to action. "Assess the impact" usually beats "make the change".

Ask what a calm, experienced project manager would do now. Gather facts, talk to the people affected, and use the project's change and risk processes.

In agile questions, favour the answer that empowers the team and delivers value in small steps. In predictive questions, favour the answer that follows the plan and controls change.

What should I do after this practice test?

Check your misses against the exam content outline, which PMI updated in July 2026, and use PMI's own materials to confirm the current question count and time.

Read the PMP exam guide for the three domains and their weights. The numbers changed in July 2026, so avoid study material that still shows the old 42, 50 and 8 percent split.

Frequently asked questions

Is this the real PMP exam?

No. These are original practice questions. The real exam is written by PMI.

Is this PMP practice test free?

Yes, with no sign-up. All 20 questions and explanations are on this page.

What changed in the PMP exam in 2026?

PMI reports a July 2026 update that rebalances the domains to People 33%, Process 41% and Business Environment 26%.

How many questions are on the PMP exam?

PMI publishes the current number and time on its exam page; it changed with the update, so check it there.

Do I need to memorise formulas?

Know the earned value formulas, the PERT estimate and the communication channels formula; they appear as short calculations.

Also preparing for the Wonderlic-style workplace aptitude test?

The LifeScore Wonderlic Pass Pack is for the Wonderlic-style workplace aptitude test, a different test, and it is not the PMP exam preparation. If you are also sitting the Wonderlic-style workplace aptitude test, full mocks on the real clocks with every answer explained are US$39, one payment, no subscription.

The CCAT Pass Pack gives you 8 full mocks on the real clock, 16 drills of 12 questions for the sections that cost you points, and a predictor that turns your mocks into the odds of reaching the target score you set. One payment, no subscription, and your free score stays free.

Prep courses for these tests usually cost $19 to $129. The CCAT Pass Pack is US$39 (£29), once.

8
timed mocks
16
topic drills
1
score predictor